Figure 1: Anticipated Sewer Work Area August 8, 2022 to August 12, 2022
The Strawberry Hill Road Sewer Expansion Project is ongoing with construction schedule update as outlined below.
Week of 8-15-2022 to 8-19-2022
- Sewer main installation on Wequaquet Lane from Strawberry Hill Road to Phinney’s Lane.
- Pump station site work at 528 Craigville Beach Road property easement. Construction access and work will occur on section of parcel fronting Strawberry Hill Road.
- Road closure and detour will be in place, with resident and business access only.
Week of 8-22-2022 to 8-26-2022
- Sewer main installation on Wequaquet Lane from Strawberry Hill Road to Phinney’s Lane.
- Pump station site work at 528 Craigville Beach Road property easement. Construction access and work will occur on section of parcel fronting Strawberry Hill Road.
- Road closure and detour will be in place, with resident and business access only.
All closed roadways will remain accessible to residents and businesses throughout construction. As always, please slow down and use extreme caution when traveling through the road construction areas, and follow posted safety and detour signs.
If you have any questions or wish to receive project updates, please contact Paul Ruszala, P.E., Senior Project Manager, at the Department of Public Works at 508-790-6400 orpaul.ruszala@town.barnstable.ma.us.
More information about the Strawberry Hill Road Project and the Town of Barnstable’s CWMP is available at: https://barnstablewaterresources.com/