The Vineyard Wind 1 Project is ongoing with construction schedule update as outlined below.

Week of 11-1-21 – 11-5-21 

  • Installation of underground splice vaults on Attucks Ln
  • Site work at the substation site (40 Communication Way)  
  • HDD (horizontal directional drilling) contractors site set up at Covells Beach (sound barrier installation and mobile office set up) 