Pavement milling and overlay work on Rt. 132 in Hyannis is scheduled to begin on Monday, October 31, 2022. The work is limited to section of Rt. 132 between Airport Rotary and the intersection with Bearses Way. A figure highlighting the limits of work is attached.

The Town’s contractor for this project is Lawrence Lynch Corporation.  Construction activities will include milling of the existing pavement surface, improvements to existing drainage structures and castings, installation of a new pavement top course, and new line striping and pavement markings.

Normal work hours will be 7:00 AM to 4:30 PM, Monday through Friday. Construction is expected to be completed by November 18, 2022, weather permitting.   

Through traffic and access to all businesses along the route will be maintained throughout construction.  Lane closures will be supported with police details to direct traffic.  Motorists are advised to seek alternate routes if possible to avoid delays.

As always, please slow down and use extreme caution when traveling through construction areas and follow posted safety and detour signs.