Figure 1:  Temporary Traffic Pattern Modifications, Week of June 20 to June 24

During the week of June 20 to June 24, from 7:30AM to 4:30 PM, Pine Street will be closed to through traffic from Main Street Centerville to West Main Street Hyannis to facilitate necessary sewer work in the intersection of Pine Street and Strawberry Hill Road.  Figure 1 indicates anticipated detours routes based upon direction of travel to or from Hyannis and Centerville/Osterville. Businesses on West Main Street and Craigville Beach Road will remain open during construction and will remain accessible via posted detours.

In addition, Strawberry Hill Road from West Main Street to Craigville Beach Road will remain closed to through traffic during the same timeframe. The closures are necessary due to work associated with the Vineyard Wind’s duct bank installation.

Formal road closure and posted detours will be in place. All closed roadways will remain accessible to residents and businesses throughout construction. As always, please slow down and use extreme caution when traveling through the road construction areas, and follow posted safety and detour signs.

Week of 6-20-2022 to 6-24-2022

  • Sewer main and main installation within the intersection of Strawberry Hill Road from Pine Street.
  • Sewer main installation on Wequaquet Lane from Strawberry Hill Road to Phinney’s Lane.
  • Pump station site work at 528 Craigville Beach Road property easement.  Construction access and work will occur on section of parcel fronting Strawberry Hill Road.  
  • Road closure and detour will be in place, with resident and business access only.

Week of 6-27-2022 to 7-1-2022

  • Sewer lateral installation on Strawberry Hill Road from Pine Street to West Main Street.
  • Sewer main installation on Wequaquet Lane from Strawberry Hill Road to Phinney’s Lane.
  • Pump station site work at 528 Craigville Beach Road property easement.  Construction access and work will occur on section of parcel fronting Strawberry Hill Road.  
  • No work scheduled July 1.
  • Road closure and detour will be in place, with resident and business access only.

Week of 7-4-22 to 7-8-22

  • No work scheduled.