*UPDATED* STRAWBERRY HILL RD SEWER EXPANSION PROJECT.  The Strawberry Hill Road Sewer Expansion Project is ongoing with construction schedule update as outlined below.

Week of 5-23-2022 to 5-27-2022

  • Sewer main and force main installation on Strawberry Hill Road from Old Town Road to Route 28.
  • Road closure and detour will be in place, with resident and business access only.

Week of 5-30-2022 to 6-3-2022

  • No work scheduled for Memorial Day (May 30)
  • Sewer main installation in Phinney’s Lane and Wequaquet Lane intersection.
  • Sewer main and force main installation on Strawberry Hill Road from Pine Street to Route 28.
  • Road closure and detour will be in place, with resident and business access only.

Week of 6-6-2022 to 6-10-2022

  • Sewer main and force main installation on Strawberry Hill Road from Pine Street to Route 28.
  • Road closure and detour will be in place, with resident and business access only.

All closed roadways will remain accessible to residents and businesses throughout construction. As always, please slow down and use extreme caution when traveling through the road construction areas, and follow posted safety and detour signs.

If you have any questions or wish to receive project updates, please contact Paul Ruszala, P.E., Senior Project Manager, at the Department of Public Works at 508-790-6400 or paul.ruszala@town.barnstable.ma.us.

More information about the Strawberry Hill Road Project and the Town of Barnstable’s CWMP is available at:  https://barnstablewaterresources.com/