*UPDATED* VINEYARD WIND 1 PROJECT. The Vineyard Wind 1 Project is ongoing with construction schedule update as outlined below.
Week of 5/16/2022 – 5/20/2022
- Site work at the substation site (40 Communication Way)
- Drainage work on Strawberry Hill Rd
- Duct bank installation on Craigville Beach Rd
Week of 5/23/2022 – 5/27/2022
- Site work at the substation site (40 Communication Way)
- Duct bank installation on Craigville Beach Rd
- Drainage work on Craigville Beach Rd
Strawberry Hill Rd, Centerville
Vineyard Wind and its contractor, Lawrence Lynch, will be conducting watermain relocation work within Strawberry Hill Rd. A police detail will be present to manage traffic. Operations active between 7:00am-3:30pm Monday – Friday, weather permitting.
Vineyard Wind and its contractor, Lawrence Lynch, will be conducting watermain relocation work within Wequaquet Ln. A police detail will be present to manage traffic. Operations active between 7:00am-3:30pm Monday – Friday, weather permitting.
Craigville Beach Rd, Centerville
Vineyard Wind and its contractor, Lawrence Lynch, installing duct bank on Craigville Beach Rd. A police detail will be present to manage traffic. This activity will take place from 7:00am – 3:30pm Monday – Saturday, weather permitting.
Vineyard Wind and its contractor, Lawrence Lynch, will be conducting parking lot restoration in the Covell’s Beach parking lot. This activity will take place from 7:00am – 3:30pm Monday – Saturday, weather permitting.
40 Communication Way, Hyannis, MA
Vineyard Wind and its contractors continue to modify the substation site at 40 Communication Way. Activity will occur between 7:00am-3:30pm Monday – Friday, weather permitting.
If you have any questions regarding the Vineyard Wind 1 Project, contact Tess Dunleavy at TDunleavy@vineyardwind.com