*UPDATED* VINEYARD WIND 1 PROJECT.  The Vineyard Wind 1 Project is ongoing with construction schedule update as outlined below.

Week of 5/16/2022 – 5/20/2022

  • Site work at the substation site (40 Communication Way)
  • Drainage work on Strawberry Hill Rd
  • Duct bank installation on Craigville Beach Rd

Week of 5/23/2022 – 5/27/2022

  • Site work at the substation site (40 Communication Way)
  • Duct bank installation on Craigville Beach Rd
  • Drainage work on Craigville Beach Rd

Strawberry Hill Rd, Centerville

Vineyard Wind and its contractor, Lawrence Lynch, will be conducting watermain relocation work within Strawberry Hill Rd. A police detail will be present to manage traffic. Operations active between 7:00am-3:30pm Monday – Friday, weather permitting.

 

Wequaquet Ln, Centerville

Vineyard Wind and its contractor, Lawrence Lynch, will be conducting watermain relocation work within Wequaquet Ln. A police detail will be present to manage traffic. Operations active between 7:00am-3:30pm Monday – Friday, weather permitting.

 

Craigville Beach Rd, Centerville

Vineyard Wind and its contractor, Lawrence Lynch, installing duct bank on Craigville Beach Rd. A police detail will be present to manage traffic. This activity will take place from 7:00am – 3:30pm Monday – Saturday, weather permitting.

 

Covell’s Beach Parking Lot

Vineyard Wind and its contractor, Lawrence Lynch, will be conducting parking lot restoration in the Covell’s Beach parking lot. This activity will take place from 7:00am – 3:30pm Monday – Saturday, weather permitting.

 

40 Communication Way, Hyannis, MA

Vineyard Wind and its contractors continue to modify the substation site at 40 Communication Way. Activity will occur between 7:00am-3:30pm Monday – Friday, weather permitting.

 

If you have any questions regarding the Vineyard Wind 1 Project, contact Tess Dunleavy at TDunleavy@vineyardwind.com