*UPDATED* Vineyard Wind 1 Project.  The Vineyard Wind 1 Project is ongoing with construction schedule update as outlined below.

Independence Dr, Hyannis

Vineyard Wind and its contractor, Lawrence Lynch, will be installing the underground duct bank within Independence Dr during the week of January 10. One lane of traffic will be closed with a police detail present to manage traffic. Operations active between 7:00am-3:30pm Monday – Friday, weather permitting.

Covell’s Beach Parking Lot

Vineyard Wind and its contractors will be in preparation for Horizontal Directional Drilling (HDD) at Covell’s Beach Parking Lot. This activity will take place from 7:00am-7:00pm Monday – Saturday, weather permitting.

40 Communication Way, Hyannis, MA

Vineyard Wind and its contractors continue to modify the substation site at 40 Communication Way. Activity will occur between 7:00am-3:30pm Monday – Friday, weather permitting.