Comprehensive Wastewater Management Plan (CWMP) Sewer Expansion Project
Construction Schedule – Weekly Update
The Strawberry Hill Road and Route 28 East Sewer Expansion Projects are ongoing with construction schedule update as outlined below.
Week of 12/12/22 to 12/16/22
- Sewer Main Installation
Sewer main installation will progress at two locations: on Phinney’s Lane from Huckins Neck Road to Longview Drive as well as Phinney’s Lane from Route 28 to Great Marsh Road. Road closure and detour will be in place, as shown in Figure 1, below. All closed roadways will remain accessible to residents and businesses throughout construction.
- Sewer Pump Station
Sewer pump station work will occur at 528 Craigville Beach Road and 1456 Falmouth Road/ Route 28.
Week of 12/19/22 to 12/23/22
- Sewer Main Installation
Sewer main installation will progress at two locations: on Phinney’s Lane from Huckins Neck Road to Longview Drive as well as Phinney’s Lane from Route 28 to Great Marsh Road. Road closure and detour will be in place, with resident and business access only.
- Sewer Pump Station
Sewer pump station work will continue at 528 Craigville Beach Road and 1456 Falmouth Road/ Route 28.
- Horizontal Directional Drilling on Route 28
Starting, Monday 12/19/22, horizontal directional drilling will occur at the intersection of Route 28 and Strawberry Hill Road. Strawberry Hill Road from West Main Street to Route 28 and from Route 28 to Wequaquet Lane will need to be closed to accommodate this work. Traffic on Route 28 will not require a detour. Additional details and a full traffic management plan to come.
All closed roadways will remain accessible to residents and businesses throughout construction. As always, please slow down and use extreme caution when traveling through the road construction areas, and follow posted safety and detour signs.

If you have any questions or wish to receive project updates, please contact Paul Ruszala, P.E., Senior Project Manager, at the Department of Public Works at 508-790-6400 or paul.ruszala@town.barnstable.ma.us.