Strawberry Hill Road will continue to experience roadwork impacts from Craigville Beach Road to Pine Street as Vineyard Wind completes necessary milling and paving operations. Localized traffic is anticipated to be reduced to a single-lane alternating and work is expected to take three weeks to complete, dependent on weather. Traffic control will be onsite to assist in directing motorists.

This activity marks the first phase of post-construction restoration along Strawberry Hill Road. Rebuilding of the shoulders, including loam and seeding, is anticipated at a later date. As always, please slow down and use extreme caution when traveling through the road construction areas, and follow available traffic control, posted safety, and detour signs.