Vineyard Wind 1 Project Construction Schedule – Weekly Update

Week of 11/28/2022 – 12/2/2022

  • Site work at the substation site (40 Communication Way)
  • Installation of water main services between Pine St and West Main St (dependent on pressure and chlorination test results)
  • Duct Bank Installation crossing Pine Street (to take place after water services are installed)
  • TJB to vault 1A pull (dependent on onshore cable pull completion)
  • Trench backfill at Covells Beach

Week of 12/5/2022 – 12/9/2022

  • Site work at the substation site (40 Communication Way)
  • Installation of water main services between Pine St and West Main St (dependent on pressure and chlorination test results)
  • Duct Bank Installation crossing Pine Street (to take place after water services are installed)

TJB to vault 1A pull (dependent on onshore cable pull completion)