Vineyard Wind will continue site work at the substation, located at 40 Communication Way in Hyannis. Additionally, Vineyard Wind will be conducting construction activities including duct bank construction and water services at multiple construction sites.

  • Duct Bank Construction on Phinney’s Lane

Starting Monday, March 20 from 7:00AM to 4:00PM, Vineyard Wind will begin the installation of duct bank on Phinney’s Lane. Construction is anticipated to begin between Wequaquet Lane and Aurora Avenue and will proceed north. As a result, Phinney’s Lane will be closed to thru traffic from Strawberry Hill Road to Route 132, as shown in Figure 1. All closed roadways will remain open to local resident and emergency traffic only.

  • Water Services

From Monday, March 20, through Friday, March 24, 2023, Vineyard Wind will continue water service relocation on Phinney’s Lane, requiring traffic to be reduced to single-lane alternating. This work will be occurring within the Phinney’s Lane road closure, from Strawberry Hill Road to Route 132, as shown in Figure 1.