Running through Friday, December 9, 2022, Vineyard Wind will be conducting construction activities including cable pulling, duct bank installation and water service work at three construction sites. Activity will occur between 7:30AM to 4:00PM, weather permitting.
Cable Pulling, through Friday, December 9, 2022
Vineyard Wind will be pulling electrical cable between valve vaults along Independence Drive and Attucks Lane. During this time, a one lane closure for both Independence Drive and Attucks Lane will be implemented, as shown in Figure 1 below. A single lane of travel is anticipated to remain open in both directions throughout the work.
Water Services, through Friday, December 9, 2022
Vineyard Wind will be installing water services on Strawberry Hill Road between Pine Street and West Main Street as well as on Strawberry Hill Road between West Main Street and Route 28. Formal road closure and posted detours will be in place, as shown in Figure 2 below. All closed roadways will remain accessible to residents and businesses throughout construction.
Duct Bank Installation, Wednesday December 7, 2022 through Friday, December 9, 2022
Pine Street will be closed to thru traffic from Main Street to West Main Street to facilitate Vineyard Wind’s duct bank installation in the intersection of Pine Street and Strawberry Hill Road, as shown in Figure 2. All closed roadways will remain accessible to residents and businesses throughout construction.
Police details are scheduled to assist in directing traffic at each location. As always, please slow down and use extreme caution when traveling through the road construction areas, and follow posted safety and traffic signs.
If you have any questions or wish to receive project updates, please contact Michael Tieu, P.E., Assistant Town Engineer, at the Department of Public Works at 508-790-6400 or Michael.Tieu@town.barnstable.ma.us